UC Riverside has received approval for the next phase in its ambitious North District housing development, with plans to break ground next spring on a 1,313-bed project.
The UC Board of Regents voted Nov. 18 to approve $443 million for North District Phase 3, which consists of three apartment-style buildings that total 440,000 square feet over 6 acres.
The approval clears the way for UCR to begin construction in early 2027 and complete the complex in summer 2029 in time for that year’s fall quarter.
The campus began developing the 51-acre site, formerly occupied by World War II era housing, in 2019. North District Phase 1, with 1,500 beds in two buildings, opened in fall 2021. Phase 2 opened last year with 1,568 beds including some reserved for Riverside Community College District students as part of a unique partnership to increase and support transfer students.
With the North District projects and the 820-bed Dundee Residence Hall, which opened in 2020, UCR has continued to grow student housing over the past decade. However, demand continues to outpace housing construction as student enrollment grows, a project report stated.
In fall 2025, UCR enrolled a record 8,300 students and in fall 2026 it welcomed about 7,800 students. Its current total student enrollment is at 27,702. By 2035, total enrollment is expected at 35,000 in alignment with the campus’ long range development plan.
In a presentation to the Regents Finance and Capital Strategies Committee before the vote. Chancellor S. Jack Hu said the long-term goal is to increase the percentage of students who can live on campus from 36 percent to 40 percent. North District Phase Three is an important step in helping reach that goal, he said.
“For UC Riverside, student housing is more than just capital investment,” he said. “It’s an investment in our student success by providing students with affordable housing close to academic resources, mentoring, campus services, and opportunities for engagement. We’re creating an environment that supports student wellbeing, academic achievement, and timely graduation.”
The new project would be built at the southern end of the site near Blaine Street between the two existing housing complexes.
It will have a total of 406 units with studio, two-bedroom, and four-bedroom options. The complex will include amenities such as study and lounge rooms, a gym, laundry facilities, and pedestrian pathways. A central park that was built as part of phase 2 will be expanded by another 1.2 acres.
“The architectural design builds upon the campus vernacular and precedent of North District 2, with respect for access to natural daylight, solar orientation, and shaded walkways,” said Jacqueline Norman, campus architect and associate vice chancellor.
The project also includes the construction of a central utility plant for heating and cooling and a 2,000-space parking structure on Blaine Street. Both are expected to serve the new development as well as future phases of North District, which plans for a total of five phases.